WEEK 4:
This week I continued on the my work on pack and winding consumables.
main highlights for this week were:
Follow up with Winder workshop and pack room about my reports and recommendations.
I went to the spinning section. Observed the important consumables.
spinning uses the most costly consumable(in terms of cost incurred in 1 yr.) : Aeron silicon spray. there were also other consumables like stick wipe. both the items were used in spinnnerette cleaning which is done every two days on every machines.
I observed the proactive maintenance being carried on and reported my observations to spinning Head.
I also worked on SAP to get valuable information about these consumables.this was also included in the report.
I also prepare the mid term report for the institute.
I also visited the Effluent tratment plant for the same.A day was spend on the induction of tankfarm and ETP